is the difference between the finish date of the last activity on the critical path and the project completion date.
a. Lag time
b.Control limit
c. Total float
d.Contingency time
e.Forward pass

Respuesta :

Otras preguntas

How did Roosevelt's policies help the conservation of natural resources?
Peter and Rosemary Grant a. spent more than 30 years studying Darwin’s tortoises. b. studied the migration of the camel. c. actually observed evolution by natur
what is x ? 4x+8y =64
state how substrate size ad ph influence enzyme activity
How do magnetic patterns in the rocks along the mid-oceanic ridges explain seafloor spreading? A. As oceanic crust sank beneath continental crust, the cooling
When did Silk get discovered
Define and Compare Boiling point, Melting point, and Freezing point.
What are the solutions to the equation x2 = 81?   A. 40.5 only
What are the square roots of 196?   A. 13 and –13
what did queen isabella have to overcome in her life