Process Id

Arrival time

Burst time

P1

3

1

P2

1

4

P3

4

2

P4

0

6

P5

2

3
If the CPU scheduling policy is Shortest Job First (SJF) preemptive, draw Gantt chart, calculate the average waiting time and average turnaround time.

Respuesta :

Otras preguntas

Which of the following statements about geographic boundaries is false? a. Geometric boundaries can lead to conflict when they cross or ignore obvious physical
In what direction will this arrow point after it is rotated 270 degrees counterclockwise
what are the basic needs of all cells in the body
what is the longest river
What are some physical properties of matter
Organisms can be classified in the same species by morphology and ___
what happent march 22,2016
A right triangle has the hypotenuse c = 12 cm and an angle A = 30°. Find the length of side a, which is opposite angle A. A. 7.4 cm B. 4 cm C. 2.5 cm D.
explain what force caused the movement of the continets from one supercontinet to their present positions
Write 0.5 in words.?write 0.5 in words? Write 0.5 in words?