The critical path on a project can change as the project progresses. select one:

a. true

b. false

Respuesta :

mirrorkitten
mirrorkitten mirrorkitten
  • 02-04-2019

The answer is True.

In project management, critical path refers to a sequence of stages that would require the smallest amount of time possible to bring a project to completion.

Critical path can change during a project since there might be circumstances during it which would lead certain activities to be finished longer or faster. Critical path can be determined by a specialized algorithm technique.

Answer Link

Otras preguntas

A garden has eight equal sides and perimeter of 56 meters. Circle the equation that gives the length, in meter, of each sides.
What were the effects of Thomas Edison's light bulb?
Why are earthquakes and volcanoes common along the ring of fire?
What is 2.1 as a fraction?
what is the approximate distance between Iraq and Afghanistan?
q-12=89 what is the value of q
How do you simplify √−81x6?
Read the sentence below, and answer the question that follows. The software program crashed in the middle of the exercise and would not restart. What word doe
As the president in the executive department implement in enforce a law they might need?
in your own words explain two functions of a public protector