If 10 men can complete a piece of work in 30 days how many men are requiredto complete the same job in 25 days?

Respuesta :

AL2006
AL2006 AL2006
  • 22-07-2014
We must assume that all workmen work at the same rate, and keep it up forever.

More men ==> fewer days

so the proportion is:    30/25 = x/10

Cross-multiply the proportion:

300 = 25 x

Divide each side by 25 :

x = 300/25 = 12 men
Answer Link

Otras preguntas

which vehicle is most likely to be fuel efficient? a) SUV (sport-utility vehicle) b) 1978 station wagon c) gas electric hybrid car d) pickup truck
Select the THREE statements that are true of the Spanish exploration and conquests in the New World. a They found a waterway through Central America to the Paci
Suppose a population of 250 crickets doubles in size every 6 months. How many crickets will there be after 2 years? A. 1,000 crickets B. 2,000 crickets C. 4,000
1.)What is the only solution of 2x^2 + 8x = x^2 – 16?
Which sentence uses correct capitalization? A. The Bill of Rights was ratified during George Washington's presidency. B. I watched the Winter olympics with my
In Romeo and Juliet where will Romeo go
What similarities do you see between the United States today and the United States of the past? What issues and problems do we continue to grapple with? What su
A pint is what fraction of a quart
In which period did nomadic people hunt animals and gather fruit for food? Neolithic Paleolithic Mesolithic
what is the partial pressure of oxygen?