If A completes a particular work in 8 days and B the same work in 24 days. How many days will it take if they work together?

Respuesta :

Аноним Аноним
  • 25-02-2018
A:
1 day = 1/8 of work

B:
1 day = 1/24 of the work

Together:
 1 day = A + B = 1/8 + 1/24 = 4/24 = 1/6

1 day = 1/6 of work
1/6 x 6 of work = 1 x 6 days
work =  6 days 

Answer Link

Otras preguntas

5. When Proctor says, "I do think I see some shred of goodness in John Proctor, Not enough to weave a banner with, but white enough to keep it from such dogs",
How to solve this? Please explain your answer! Thanks!
KINDLY SEE ATTACHED! please help with this​ question.
Which of the following controls adduction at the shoulder? O subscapularis supraspinatus O infraspinatus teres major O teres minor
Suppose that y varies directly with x and y=12 when x=-2. What is x when y=-6 Please help me!!
Essay on importance of teaching in our daily life
A 30​-inch piece of steel is cut into three pieces so that the second piece is twice as long as the first​ piece, and the third piece is two inches more than fo
True or false Bacteria, fungi, and other organisms that break down waste are called consumers.
A biker’s speed is 1.5 times faster than a walker’s speed. They start moving simultaneously in the same direction from the same point and, after 1.5 hours, the
Was the enclaves positive for immigrants